SDF Engineering/ Industrial and Supply

Karoun 1 hydro power plant , Khuzestan Water & Power Authority

Karoun 1 hydro power plant , Khuzestan Water & Power Authority , Electromechanical & hydromechanical equipment

Blog

Client:

Khuzestan Water & Power Authority

Sub Contractor: Sadaf Teknik Endüstri
Location: Khuzestan, Iran
Scheme: PC

Scope: Electromechanical & hydromechanical equipment

Khuzestan Water & Power AuthorityKhuzestan Water & Power Authority

  • Capacity: 1,000 MW (4 Units of 250 MW)
  • Type of power house: Underground
  • Average annual power generation: 4000 GWh

 

Main equipment:

  • Turbine: Vertical Francis, 187.5 rpm, 650 tons each
  • Generator: Synchronous type, 15.75 KV
  • Butterfly valve: 5 m inner outlet dimameter, 275 tons each unit
  • Governor: Digital type with digital backup governors, 70 bar
  • Transformer: Single phase step up transformers, 100 MVA
  • Hydromechanical equipment: Gates, penstock, steel lining, trash rack and related equipment
  • Crane: 2 power house main cranes, 320 tons each
     

© Copyright 2026 Sadaf Teknik